Salient Features of Sardar Sarovar Project

       Dam and Powerhouse:

Dam:

Click On the Map to See an Enlrged Image
Click on the image to view the enlarged form
 

1) Location

Lat 73 .45' E

 

Long 21 .50' N

 

5.6 Km upstream of Navagam village and 120 Km upstream of Bharuch Town,

2) Type of Dam

Concrete Gravity

3) Length

1210 m

4) Top level of dam

146.50m (480.6 ft)

5) Max. height above Foundation

163 m
   
Spillway  

1.Type

Ogee

2.Clear waterway

420.9 m

3. Crest level

121.92 m (400 ft)

4..Gates

 

Type

Radial

No & size

30 - 7 Nos. in auxiliary spillway 18.3 m x 18.3m (60'x60') 23 nos in service spillway 18.3 m x 16.76 m (60'x55')

5.Discharge Capacity

84949 cumec (30 lakh cusec)
   

Sluices

 
1.Construction Sluices

10 nos. at EL 18m 2.10 x 2.74m to discharge 268 cumec
(plugged in February, 1994)

2.River Sluice

4 nos. at EL 53 m 2.5 x 3.5 m with discharge 1068 cumec at FRL.
Proposed Irrigation
Bye pass tunnel
2 nos. 5.5 m dia at EL 88.39 m (290 ft) invert level to discharge 15000 cusec at MDDL .

   
Rock Fill Dam  
1.Numbers 4
2.Length 2567 m total
3.Top R.L 102.6 m (336.5 ft)
4.FPL 95.10 m (312 ft)
5.Low Water Level 83.8 m (275 ft)
6.Storage at FRL 63.39 Mcum

Power House:


Click on the image to view the enlarged form
 

1.River Bed Power House (RBPH)

6x200 MW = 1200 MW
2.Canal Head Power House(CHPH) 5x50 MW = 250 MW
3.Total Installation 1450 MW
4.Power benefits:  
RBPH Firm 3635 Gwh reducing to Zero After 45 years.
  Secondary 1431 Gwh reducing to 520 Gwh 45 years.
CHPH Firm 213 Gwh increasing to 440 Gwh After 45 years.
  Secondary 190 Gwh increasing to 345 Gwh After 45 years.

 